Austin permit applications: the 45-day completeness rule
Forty-five days to be complete
This is the one hard permit deadline actually written into Austin's code, and it runs against you, not the City.
For a building or demolition permit, §25-1-82(E) provides that the application is accepted as complete when the applicant has paid the required fee and provided the required information — and it must happen no later than the 45th day after the application is submitted.
Miss it and the application expires. You may submit updates and correct deficiencies at any point before that day, but not after.
The City owes you a written deficiency list in 10 working days
The obligation runs both ways. Under §25-1-82(E)(2), if your application is rejected as incomplete, the responsible director or building official must give you a written explanation that identifies the deficiencies and the information needed to complete it — within 10 working days after the application is received.
So a silent rejection is not compliant. If the clock is running and no written deficiency list has arrived, that is worth raising rather than waiting.
There is also a release valve at §25-1-82(B): the director or building official may let you omit required information they determine is not material to the decision. If they refuse, that determination can be appealed to the city manager.
Site plans run on the same 45 days, plus a one-year outer limit
Site plan applications have their own limb of the same section, and two extra numbers worth holding:
- the application is complete once the fee is paid and the required information provided, again no later than the 45th day;
- a certification that the site plan application is administratively complete is valid for 45 days from issue; and
- the application itself expires one year after submission unless it has been approved, or the director has granted additional days for an update under §25-1-90(A) — in which case the expiry moves by exactly the days granted.
The certification having its own 45-day life is the trap. A stale certification means the director may not review the application, and the same applies if the submitted site plan no longer matches the certified materials.
How we keep applications alive
We treat the 45 days as the real deadline, because it is the only one the code guarantees. Everything else — review length, comment cycles — is governed by state law timeframes and departmental rules rather than a number we can point to.
The practical habit is to get the deficiency list early and in writing. Ten working days is the entitlement, and an application that has gone quiet is usually an application where something was never formally rejected and the clock is running anyway.
On site plans, we diary the certification date separately from the submission date. Forty-five days is short, and a certification that lapses while a consultant finishes a drawing is an avoidable restart.
Common questions
Send us an address and we will tell you what we find
We do this research ourselves on every project we take on — zoning, floodplain, watershed, trees, whether it is a legal lot. Send us an address and we will run it and tell you what we find. It works the same whether you own a vacant lot, a house you are thinking of adding a unit to, or a house you are thinking of replacing. No charge and no strings, and if it is a bad lot we will say so.
Send us an addressWe are homebuilders, not the City of Austin. This page explains how we read the code in practice — it is not legal advice and it is not an official determination. Always confirm with Austin Development Services before you rely on it for a project. The authoritative text is the Austin Land Development Code; permitting questions go to Austin Development Services Department.