How much does an Austin building permit cost? The adopted fee schedule, line by line
There is no such thing as "the" Austin permit fee, and the schedule says so by its layout
Search for what an Austin building permit costs and you will get a single confident number, usually to the cent. It is worth understanding why those numbers disagree with each other so wildly, because the reason is structural rather than a matter of anyone being careless.
Austin prices a house across five separate permits. The residential fee sheet, under the heading Single Family, Duplex, Townhouse, and other Residential Structures, sets out Building, Electrical, Mechanical, Plumbing and Energy as five distinct lines. Each has its own base fee. Each has its own rate per additional square foot. And the square-foot bands step at 1,000, 2,000, 3,000, 4,000 and 5,000 square feet.
The sheet prints no total for them. This is the detail that explains the whole mess. Sheets 1 through 4 of the schedule each carry a Total column. The five-trade table on sheet 5 does not — it lists the five lines and stops. So every "Austin permit costs $X" figure you have read is somebody's arithmetic over some subset of those lines, plus or minus plan review, plus or minus the per-case charges further down. None of them is a number the City publishes, and none of them says which subset it added.
Plan review is charged separately, and earlier. The schedule states that the review fee is payable at the time of submittal and is non-refundable unless collected in error, while the permit fee is payable at the time of permit issuance for building and trade permits. Two payments, at two different moments, from two different parts of the schedule. A quote that gives you one number has silently merged them.
| Trade permit | Base fee | 1,001–2,000 sq ft | 2,001–3,000 sq ft | 3,001–4,000 sq ft | 4,001–5,000 sq ft | 5,001+ sq ft |
|---|---|---|---|---|---|---|
| Building | $289.53 | $289.53 + $0.05760/sq ft | $347.12 + $0.0576/sq ft | $404.70 + $0.04570/sq ft | $450.37 + $0.02810/sq ft | $478.50 + $0.02879/sq ft |
| Electrical | $166.99 | $185.94 + $0.0234/sq ft | $209.38 + $0.02340/sq ft | $232.82 + $0.02340/sq ft | $256.26 + $0.01250/sq ft | $268.76 + $0.01969/sq ft |
| Mechanical | $116.07 | $116.07 + $0.0137/sq ft | $123.88 + $0.0053/sq ft | $129.15 + $0.0123/sq ft | $141.48 + $0.02470/sq ft | $166.17 + $0.01233/sq ft |
| Plumbing | $200.43 | $203.17 + $0.02880/sq ft | $231.96 + $0.02880/sq ft | $260.74 + $0.02680/sq ft | $287.51 + $0.01880/sq ft | $306.26 + $0.02750/sq ft |
| Energy | $65.80 | $65.80 + $0.00/sq ft | $65.80 + $0.00/sq ft | $65.80 + $0.00/sq ft | $65.80 + $0.00/sq ft | $65.80 + $0.00/sq ft |
Sheet 5 of 6, "Single Family, Duplex, Townhouse, and other Residential Structures". In each band the per-square-foot rate applies to area over the band floor — over 1,000 sq ft in the 1,001–2,000 band, over 2,000 in the next, and so on. The first column is headed simply "Base Fee" in the schedule, with no square-foot range printed against it. The schedule prints no combined total for these five lines.
Plan review: the other half of the bill, paid at submittal
Plan review sits on sheet 1 of the residential schedule and is charged on its own square-foot ladder, in different bands from the trade permits. For new construction the steps are at the same thousand-foot marks, but the rate is an order of magnitude larger: $0.18 per square foot in every band up to 5,000 sq ft.
Every project also pays a $106.72 Residential Plan Review Application Processing Fee before any of this. And on a project with more than two structures or more than two dwelling units, plan review adds $130.68 per additional structure and $130.68 per additional dwelling unit beyond the second — which is worth knowing before you decide how many units to build.
| Plan review — one and two family dwellings | Fee |
|---|---|
| Residential Plan Review Application Processing Fee | $106.72 |
| Express Residential Plan Review | $106.72 |
| New construction — base fee | $896.50 |
| 1,001–2,000 sq ft | $1,075.80 plus $0.18/sq ft over 1,000 |
| 2,001–3,000 sq ft | $1,255.10 plus $0.18/sq ft over 2,000 |
| 3,001–4,000 sq ft | $1,434.40 plus $0.18/sq ft over 3,000 |
| 4,001–5,000 sq ft | $1,613.70 plus $0.18/sq ft over 4,000 |
| 5,001 sq ft and above | $1,793.00 plus $0.018/sq ft over 5,000 — as printed |
| each additional structure over 2 | $130.68 |
| each additional dwelling unit over 2 | $130.68 |
| Addition / remodel — base fee | $179.30 |
| 101–200 sq ft | $358.60 plus $1.35/sq ft over 100 |
| 201–300 sq ft | $537.90 plus $1.35/sq ft over 200 |
| 301–400 sq ft | $717.20 plus $1.35/sq ft over 300 |
| 401–500 sq ft | $896.50 plus $1.35/sq ft over 400 |
| 501 sq ft and above | $1,075.80 plus $0.135/sq ft over 500 |
| Interior remodel — base fee | $120.78 |
| 101–200 sq ft | $120.78 plus $1.08/sq ft over 100 |
| 201–300 sq ft | $241.56 plus $1.08/sq ft over 200 |
| 301–400 sq ft | $362.34 plus $1.08/sq ft over 300 |
| 401–500 sq ft | $483.12 plus $1.08/sq ft over 400 |
| 501 sq ft and above | $603.90 plus $0.54/sq ft over 500 |
| Small projects garage conversions, carport and porch enclosures, amnesty CO, fences, pools | $132.86 each |
| Resubmittal | $532.52 |
| Minor plan revision administrative changes needing no graphic exhibits | $84.15 |
| Major plan revision revised plans, or modified calculations | $532.52 |
Sheet 1 of 6 (plan review ladders and small projects) and sheet 2 of 6 (resubmittal and revisions); the minor/major revision definitions are the schedule's own footnotes A and B on sheet 6 of 6. The $0.018 in the top new-construction band is reproduced exactly as printed — the same one-tenth step appears in the addition/remodel ladder ($1.35 then $.135), so it is the sheet's pattern rather than a stray decimal.
One worked total, with the arithmetic shown
Here is the part every competing page gets to skip. Below is a single total for a 2,400 sq ft new house — 400 square feet into the 2,001–3,000 band — built by adding seven printed lines. This is our arithmetic, not a figure the City publishes. That is exactly the point: the only honest way to state an Austin permit total is to show which lines went into it, so you can re-add them or swap in your own square footage.
| Line | Sheet | Arithmetic | Amount |
|---|---|---|---|
| Residential Plan Review Application Processing Fee | 1 of 6 | flat | $106.72 |
| Plan review — new construction, 2,001–3,000 sq ft | 1 of 6 | $1,255.10 + 400 × $0.18 | $1,327.10 |
| Building permit | 5 of 6 | $347.12 + 400 × $0.0576 | $370.16 |
| Electrical permit | 5 of 6 | $209.38 + 400 × $0.0234 | $218.74 |
| Mechanical permit | 5 of 6 | $123.88 + 400 × $0.0053 | $126.00 |
| Plumbing permit | 5 of 6 | $231.96 + 400 × $0.0288 | $243.48 |
| Energy permit | 5 of 6 | $65.80 + 400 × $0.00 | $65.80 |
| Added together | — | our arithmetic — the City publishes no such total | $2,458.00 |
Every input is a line item from the archived FY 2025-26 residential fee sheet; only the addition is ours. What this figure excludes: Austin Energy service fees, fire review and the fire certificate of occupancy inspection, tree review and inspection, any floodplain or engineering review, every reinspection, and everything outside this schedule entirely — Austin Water tap and capital recovery fees, parkland dedication and utility connection costs. It also assumes all five trade permits are pulled; the schedule prices five lines but does not say a project must take all five.
The charges that actually move the number, and the schedule flags them as conditional
Sheet 3 of the schedule opens with a sentence worth quoting in full, because it is the reason no honest quote is a single number: the fees listed there "may or may not apply and are considered on a per case basis in relation to elements involved in the proposed project application packet."
These are the ones that most often turn a predictable bill into an unpredictable one. Whether they apply depends on your lot, not on your house.
| Conditional charge | Fee | When it bites |
|---|---|---|
| Building Service Planning Application Review Fee Austin Energy | $200.00 + $20.00 AE 10% technology fee $220.00 | Electric service planning |
| Electric Service Application Fee Austin Energy | $200.00 + $20.00 $220.00 | New or changed electric service load |
| Fire residential code permit review | $125.00 | Residential fire review |
| Fire final (certificate of occupancy) inspection | $370.00 plus $148/hour beyond 1 hour onsite | At CO |
| Wildland urban interface fire plan review | $250.00 | Lots in the wildland urban interface |
| Wildland urban interface fire inspection | $444.00 | Same |
| Tree plan review | $515.39 update fee $277.45 | Protected or heritage trees on site |
| Tree inspection | $569.16 new construction $367.84 all other residential | Same |
| Heritage tree review variance | $1,196.56 administrative $4,997.48 commission | Removing or encroaching on a heritage tree |
| Floodplain review | $110.00 initial $470.00 detailed | Lot touches a floodplain |
| Erosion hazard zone review | $304.97 preliminary $813.26 detailed | Creekside lots |
| Grading and drainage review | $304.97 preliminary $813.26 detailed | Where required |
| Floodplain variance | $1,431.00 administrative $4,715.00 Council | Rarely, and expensively |
| Reinspection | $76.23 per inspection | See below |
| After hours inspection | $157.34 per hour, 1 hour minimum | Out-of-schedule inspections |
| Demolition | $97.02 processing · $73.70 permit · $55.00 predemolition inspection | Demolition is its own permit |
| Relocation permit | $52.80 | Moving a structure |
| Temporary certificate of occupancy building only, expires after 90 days | $71.50 renewal $58.30 | Moving in before final |
| Solar — auxiliary power | $32.47 intake · $111.66 electrical permit incl. AE tech fee · $74.44 inspection, 1–50 kW | Rooftop solar |
Sheets 2, 3, 4 and 6 of 6. Sheet 3 states these "may or may not apply and are considered on a per case basis". Several lines are split between Development Services and another department — the Austin Energy rows show the department fee, the 10 percent technology fee and the total the schedule prints.
What this schedule is not
Two boundaries matter more than anything in the tables above, because a reader who misses them will budget badly.
This is one sheet of several. The City publishes its FY 2025-26 fees as a set of per-discipline PDFs — commercial, site plan, subdivision, zoning, code compliance, tree, right of way and more. This page reads the residential sheet only. Nothing here tells you what a site plan or a subdivision review costs, and nothing about those sheets can be inferred from this one.
Development Services fees are not the whole bill. Austin Water tap fees and capital recovery (impact) fees, parkland dedication, and utility connection costs do not appear in this schedule at all. On a real infill project they can exceed everything on this page combined. A quote built only from the fee schedule is not a project budget.
One more, smaller: the schedule marks a number of lines with a superscript S, which it defines as "may be applicable for Smart Housing". What the programme does to those fees is not stated in the schedule and is not stated here — see Smart Housing.
What we tell owners about the number
The permit fee is almost never the thing that decides a project. A 2,400 sq ft house adds up to something in the low thousands across plan review and the five trade permits. That is real money and it is not the money that determines whether a build pencils. The conditional lines — a heritage tree, a floodplain edge, an erosion hazard zone — move faster and further than the square-foot ladders do, and they are decided by the lot before anyone draws anything.
So we price the lot's conditions first, and the square footage second. Whether a heritage tree sits in the build envelope changes the fee picture by more than adding a thousand square feet does. So does whether any part of the lot is in a floodplain or an erosion hazard zone. Those are answerable from a survey and a map before a design exists.
And we budget for reinspections rather than pretending they will not happen. $76.23 each, one included per inspection type, and a locked gate counts. On a full build the realistic assumption is not zero.
Then we re-read the schedule in October. These figures change on 1 October every year. Any number we gave you in September is a number we check again in October, and so should any number you found anywhere else.
Common questions
Want a real number for your project?
We do this research ourselves on every project we take on — zoning, floodplain, watershed, trees, whether it is a legal lot. Send us an address and we will run it and tell you what we find. It works the same whether you own a vacant lot, a house you are thinking of adding a unit to, or a house you are thinking of replacing. No charge and no strings, and if it is a bad lot we will say so.
Talk to us about your buildWe are homebuilders, not the City of Austin. This page explains how we read the code in practice — it is not legal advice and it is not an official determination. Always confirm with Austin Development Services before you rely on it for a project. The authoritative text is the Austin Land Development Code; permitting questions go to Austin Development Services Department.