Austin UNO site rules: no FAR, no coverage cap, 100% impervious cover
Four rules simply stop
Most of this hub is about limits. §25-2-763 is about limits that do not exist in West Campus, and it is a shorter list to read than to believe:
- Maximum floor-to-area ratios — do not apply.
- Maximum building coverage percentages — do not apply.
- Article 9 (Landscaping) — does not apply.
- Article 10 (Compatibility Standards) — does not apply, if the property is at least 75 feet from the boundary of the overlay.
For a multi-family use, §25-2-763(C) also removes the subchapter's minimum site area and open space requirements. What is left holding the building down is height, the envelope, and the street.
| Subdistrict | Maximum impervious cover |
|---|---|
| Inner west campus | 100% |
| Guadalupe | 100% |
| Outer west campus | The greater of 90% or the base district percentage |
| Dobie | The greater of 85% or the base district percentage |
§25-2-763(B) supersedes the subchapter's impervious cover limitations entirely.
A hundred percent means the whole lot
In the inner west campus and Guadalupe subdistricts the maximum impervious cover is 100 percent. There is no requirement to leave any of the site pervious.
Outer west campus and Dobie are written as a comparison: the maximum is the greater of 90 or 85 percent or the percentage permitted in the base zoning district. Both halves are still ceilings — nothing here obliges you to cover anything. What the "greater of" decides is which ceiling applies, and it fixes the overlay figure as the lower bound of that ceiling.
In practice the West Campus base districts permit well under 90 percent, so the working answers are simply 90 and 85. The comparison is a safety valve for a base district that one day permits more, not a live choice on most sites today.
No minimum setback, but you still cannot reach the kerb
§25-2-757(A) says there are no minimum front or street side yard setbacks — the single exception being 10 feet along Martin Luther King, Jr. Blvd. between Rio Grande and San Gabriel. Interior side and rear yards have neither a minimum nor a maximum.
Then subsection (E): a building must be at least 12 feet from the front face of the kerb and at least 30 feet from the centreline of the adjacent street. That is not a contradiction. A setback is measured from your property line; (E) is measured from the street itself, so on a narrow right-of-way it binds long before any property-line rule would.
The maximum setback, and the four ways out of it
As in the rest of the city's urban-form rules, the setback here is a ceiling of 10 feet, not a floor — the building is required to come forward. Four exceptions loosen it:
- 15 feet along 24th Street, or along MLK between Rio Grande and San Gabriel.
- 45 feet for a public plaza or private common open space.
- No maximum at all for a pedestrian entry court or an outdoor café.
- A modification by the director of the Watershed Protection and Development Review Department, where it is required to protect a historic structure or a tree the city arborist has designated significant.
The pattern is consistent: you may only step back to make somewhere for people to be, or to save something already standing.
Compatibility survives at the edges
Article 10 drops away only where the property is at least 75 feet from the boundary of the overlay. Inside that 75-foot band the compatibility standards still run, which is how the overlay meets the ordinary neighbourhoods around it.
And where compatibility does apply, §25-2-757(F) adds a requirement of its own: a building, or a solid masonry wall at least six feet high, between a public or common open space and the property that triggered the standards.
Common questions
Send us an address and we will tell you what we find
We do this research ourselves on every project we take on — zoning, floodplain, watershed, trees, whether it is a legal lot. Send us an address and we will run it and tell you what we find. It works the same whether you own a vacant lot, a house you are thinking of adding a unit to, or a house you are thinking of replacing. No charge and no strings, and if it is a bad lot we will say so.
Send us an addressWe are homebuilders, not the City of Austin. This page explains how we read the code in practice — it is not legal advice and it is not an official determination. Always confirm with Austin Development Services before you rely on it for a project. The authoritative text is the Austin Land Development Code; permitting questions go to Austin Development Services Department.